SR 572 getting new pavement between Drane Field Road and Pipkin Creek Road
FDOT is resurfacing a stretch of State Road 572 in Polk County.
The Florida Department of Transportation is resurfacing State Road 572 between Drane Field Road and Pipkin Creek Road. The work is being handled by Hubbard Construction Company under FDOT Work Program item 438013, with a contract value of approximately $4.8 million.
Work began in September 2024 and is scheduled to finish by May 2026. The project spans roughly 2.4 miles across five segments.
Timeline
Receipts β verify every claim
1 of 2 open straight to the record. The rest need a sign-in at the agency, or a search on its portal.
gis.fdot.gov FDOT Southwest Florida Roads
www.swflroads.com Β· agency portal β search for the case number