Interchange corridor
SR 559 interchange at SR 400 getting signalization and resurfacing work
FDOT is improving the SR 559 interchange where it meets SR 400 and the I-4 ramp, with signalization upgrades and road resurfacing.
The Florida Department of Transportation is working on improvements to the SR 559 interchange at SR 400 (I-4 ramp), focusing on signalization and resurfacing. The contract, awarded to C.W. Roberts Contracting, Inc., is valued at approximately $2.46 million. Work began in late October 2024 and was estimated to complete by mid-June 2025.
Timeline
Jan 31, 2024
Contract let for SR 559 resurfacing work (SR 400 to SR 33)
FDOT Work Program Item 447436
Receipts β verify every claim
FDOT Work Program Item 447436
gis.fdot.gov Southwest Florida Roads (FDOT District 1)
www.swflroads.com
gis.fdot.gov Southwest Florida Roads (FDOT District 1)
www.swflroads.com